Development and Validation of a Delay Assessment Matrix for Road and Highway Projects

  • Harish L Reddy National Institute of Construction Management and Research, Pune
  • Dr. Nagakumar M S R V College of Engineering, Bengaluru, India
Keywords: Delay, Road and Highway Projects, Monte Carlo Simulation, Factor Analysis

Abstract

The study aims to gather information and assess the extent of delays and their impact on road and highway projects in India. The objective is to develop a delay assessment matrix for easy quantification of delay causing factors on project duration. A mixed method approach was used for data collection wherein information was gathered through literature review, questionnaire survey, interviews and responses under RTI act. The collected information was screened, verified and analyzed using statistical tools. Factor analysis was employed to arrive at a final list of 22 factors grouped in a 3x3 matrix having probability of occurrence vs.  impact on project duration as the axes. The model was tested on a recently completed highway project using Monte Carlo simulation technique. The result of simulation was the increase in project schedule due to the occurrence of delays in the project in accordance with the specified probability and impact. The simulated duration of the project was in the range of 1095 days, 1229 days, and 1375 days for low, moderate and severe conditions respectively. The actual project duration was reported at 1116 days against contracted duration of 910 days. The simulated duration is found to be in close agreement with the actual duration of the project.

Downloads

Download data is not yet available.

Author Biographies

Harish L Reddy, National Institute of Construction Management and Research, Pune

Assistant Professor

Dr. Nagakumar M S, R V College of Engineering, Bengaluru, India

Professor

References

IBEF, Indian road industry report, https://www.ibef.org/industry/roads-presentation, 2021.

Department of Economic Affairs, Economic Survey 2020-21: Volume I. Ministry of Finance, Government of India, 2021. https://www.indiabudget.gov.in/economicsurvey/

Infrastructure and Project Monitoring Division, 425th Flash report on Central sector projects. Ministry of Statistics and Programme Implementation, Government of India, 2021. http://www.cspm.gov.in/english/flr/FR_Apr_2021.pdf

Elawi G, Algahtany M, Kashiwagi D, Owners’ perspective of factors contributing to project delay: Case studies of road and bridge projects in Saudi Arabia, Procedia Engineering,145:1402-1409, 2016. https://doi.org/10.1016/j.proeng.2016.04.176

Kog YC, Major construction delay factors in Portugal, the UK, and the US, Practice Periodical on Structural Design and Construction, 23(4):04018024, 2018. https://doi.org/10.1061/(ASCE)SC.1943-5576.0000389

Asiedu R, Alfen H, Understanding the underlying reasons behind time overruns of government building projects in Ghana, KSCE Journal of Civil Engineering, 20(6):2103-2111, 2015. https://doi.org/10.1007/s12205-015-0544-4

Kavuma A, Ock J, Jang H, Factors influencing time and cost overruns on freeform construction projects, KSCE Journal of Civil Engineering, 23(4):1442-1450, 2019. https://doi.org/10.1007/s12205-019-0447-x

Larsen J, Shen G, Lindhard S, Brunoe T, Factors affecting schedule delay, cost overrun, and quality level in public construction projects, Journal of Management in Engineering, 32(1):04015032, 2016. https://doi.org/10.1061/(asce)me.1943-5479.0000391

Kog YC, Project management and delay factors of public housing construction, Practice Periodical on Structural Design and Construction, 23(1):04017028, 2018. https://doi.org/10.1061/(asce)sc.1943-5576.0000350

Tengan C, Aigbavboa C, Level of stakeholder engagement and in monitoring and evaluation of construction projects in Ghana, Procedia Engineering, 196:630-637, 2017. https://doi.org/10.1016/j.proeng.2017.08.051

Kim S, Tuan K, &Luu V, Delay factor analysis for hospital projects in Vietnam, KSCE Journal of Civil Engineering, 20(2):519-529, 2015. https://doi.org/10.1007/s12205-015-0316-1

Ökmen Ö, Risk assessment for determining best design alternative in a state-owned irrigation project in Turkey, KSCE Journal of Civil Engineering, 20:109–120, 2016. https://doi.org/10.1007/s12205-015-0397-x

Mittal Y, Paul V, Rostami A, Riley M, Sawhney A, Delay factors in construction of healthcare infrastructure projects: A comparison amongst developing countries, Asian Journal of Civil Engineering, 21(4):649-661, 2020. https://doi.org/10.1007/s42107-020-00227-1

Abbasi O, Noorzai E, Gharouni JK,Golabchi M, Exploring the causes of delays in construction industry using a cause-and-effect diagram: Case Study for Iran, Journal of Architectural Engineering, 26(3):05020008, 2020. https://doi.org/10.1061/(asce)ae.1943-5568.0000431

Ruqaishi M, Bashir H, Causes of delay in construction projects in the oil and gas industry in the Gulf cooperation council countries: A case study, Journal of Management in Engineering, 31(3):05014017, 2015. https://doi.org/10.1061/(asce)me.1943-5479.0000248

Gunduz M, Nielsen Y, Ozdemir M, Fuzzy assessment model to estimate the probability of delay in Turkish construction projects, Journal of Management in Engineering, 31(4):04014055, 2015. https://doi.org/10.1061/(asce)me.1943-5479.0000261

Bagaya O, Song J, Empirical study of factors influencing schedule delays of public construction projects in Burkina Faso, Journal of Management in Engineering, 32(5):05016014, 2016 . https://doi.org/10.1061/(asce)me.1943-5479.0000443

Kog YC, Construction delays in Indonesia, Malaysia, Thailand, and Vietnam, Practice Periodical on Structural Design And Construction, 24(3):04019013, 2019 . https://doi.org/10.1061/(asce)sc.1943-5576.0000434

Niazi G, Painting N, Significant factors causing cost overruns in the construction industry in Afghanistan, Procedia Engineering, 182:510-517, 2017. https://doi.org/10.1016/j.proeng.2017.03.145

Yaseen ZM, Ali ZH, Salih SQ, Al-Ansari N, Prediction of risk delay in construction projects using a hybrid artificial intelligence model, Sustainability 12(4):1514, 2020 . https://doi.org/10.3390/su12041514

Sanni-Anibire M, Mohamad Zin R, Olatunji S, Causes of delay in the global construction industry: A meta analytical review, International Journal of Construction Management, 2020. https://doi.org/10.1080/15623599.2020.1716132

Niti Aayog, Report of the task force on project and program management. Government of India, 2019. http://www.niti.gov.in/node/706

Schoonenboom J, Johnson RB, How to Construct a Mixed Methods Research Design, KolnerZeitschrift fur Soziologie und Sozialpsychologie, 2017. https://www.ncbi.nlm.nih.gov/pmc/articles/PMC5602001

Greener S, Business Research Methods. London: Ventus Publishing, 2008.

Alsharif S,Karatas A, A framework for identifying causal factors of delay in nuclear power plant projects, Procedia Engineering, 145:1486-1492, 2016. https://doi.org/10.1016/j.proeng.2016.04.187

Alsulaiti AA, Kerbache L, Analysis of critical delay factors in construction projects with a focus on Qatar. International Journal of Business and Economics Research, 9(3):130-139, 2020. https://doi: 10.11648/j.ijber.20200903.16

Alzara M, Kashiwagi J, Kashiwagi D, Al-Tassan A, Using PIPS to minimize causes of delay in Saudi Arabian construction projects: University case study, Procedia Engineering, 145:932-939, 2016. https://doi.org/10.1016/j.proeng.2016.04.121

Dixit S, Sharma K, Factors influencing construction time delay on high rise projects in India, Proceedings of the Creative Construction Conference, Article 047, 2019. https://doi.org/10.3311/CCC2019-047

Gebrehiwet T, Luo H, Analysis of delay impact on construction project based on RII and correlation coefficient: Empirical study, Procedia Engineering, 196:366-374, 2017. https://doi.org/10.1016/j.proeng.2017.07.212

Islam M, Suhariadi B, Construction delays in privately funded large building projects in Bangladesh, Asian Journal of Civil Engineering, 19(4):415-429, 2018. https://doi.org/10.1007/s42107-018-0034-3

Jahangoshai Rezaee M, Yousefi S, Chakrabortty RK, Analyzing causal relationships between delay factors in construction projects: A case study of Iran, International Journal of Managing Projects in Business, 14(2):412-444, 2021. https://doi.org/10.1108/IJMPB-01-2019-0020

Kadry M, Osman H, Georgy M, Causes of construction delays in countries with high geopolitical risks, Journal of Construction Engineering and Management, 143(2):04016095, 2017. https://doi.org/10.1061/(asce)co.1943-7862.0001222

Kang H, Kim Y, Analysis of the probabilistic cost variation ranges according to the effect of core quantitative risk factors for an overseas plant project: Focused on a Middle East gas plant project, KSCE Journal of Civil Engineering, 20(2):509-518, 2015. https://doi.org/10.1007/s12205-015-0497-7

Magdy M, Georgy M, Osman H, Elsaid M, Delay analysis methodologies used by engineering and construction firms in Egypt, Journal of Legal Affairs and Dispute Resolution in Engineering and Construction, 11(3):04519006, 2019. https://doi.org/10.1061/(asce)la.1943-4170.0000293

Perera N, Sutrisna M, Yiu T, Decision-Making model for selecting the optimum method of delay analysis in construction projects, Journal of Management in Engineering, 32(5):04016009, 2016. https://doi.org/10.1061/(asce)me.1943-5479.0000441

Pham H, Luu T, Kim S, Vien D, Assessing the impact of cost overrun causes in transmission lines construction projects, KSCE Journal of Civil Engineering, 24(4):1029-1036, 2020. https://doi.org/10.1007/s12205-020-1391-5

Senouci A, Ismail A, Eldin N, Time delay and cost overrun in Qatari public construction projects, Procedia Engineering, 164:368-375, 2016. https://doi.org/10.1016/j.proeng.2016.11.632

Tesfahun Adugna N, A study of causes of delay and cost overrun in office construction projects in the eThekwini municipal area. Thesis, Durban University of Technology, Durban, South Africa, 2015.

Department of Economic Affairs, PPP Project Info. Ministry of Finance, Government of India, 2021. Retrieved from https://www.pppinindia.gov.in/infrastructureindia/web/guest/view- project?p_p_id=viewproject_WAR_Projectportlet&p_p_lifecycle=0&p_p_state=pop_up&p_p_mode=view&p_p_col_id=column- 1&p_p_col_count=1&_viewproject_WAR_Projectportlet_jspPage=%2Fhtml%2Fviewproject%2Fppp_all_info.jsp&_viewproject_WAR_Projectportlet_sessionId=25706

Conway JM, Huffcutt AI, A review and evaluation of exploratory factor analysis practices in organizational research. Organization Research Methods, Sage Publications, 2003.

Mundfrom DJ, Shaw DG, Ke TL, Minimum sample size recommendations for conducting factor analyses. International Journal of Testing, 5(2):159-168, 2005. http://dx.doi.org/10.1207/s1532757fijt0502-4

Howard MC, A review of exploratory factor analysis decisions and overview of current practices: What we are doing and how can we improve? International Journal of Human-Computer Interaction, 32(1):51-62, 2016. https://doi.org/10.1080/10447318.2015.1087664

Watkins MW, Exploratory factor analysis: A guide to best practice, Journal of Black Psychology Article, 1-28, 2018. https://doi.org/10.1177/0095798418771807

Kandaswamy S, The basics of Monte Carlo simulation: A tutorial. Paper presented at Project Management Institute Annual Seminars & Symposium, Nashville, TN. Newtown Square, PA: Project Management Institute, 2001.

India Infoline News Service, Sadbhav Infrastructure Project’ subsidiary receives Provisional Completion Certificate, 2020. https://www.indiainfoline.com/article/news-sector-cap-goods-eng-infra/sadbhav-infrastructure-project%E2%80%99-subsidiary-receives-provisional-completion-certificate-120072400739_1.html

Published
2021-10-09
How to Cite
Reddy, H., & M S, N. (2021). Development and Validation of a Delay Assessment Matrix for Road and Highway Projects. PREPARE@u® | IEI Conferences. https://doi.org/10.36375/prepare_u.iei.a111